The design process for a concrete mini golf course is accomplished in several stages:
- Design conference call with owner defining what AGS will need in order to proceed with the design and to obtain the owner’s vision and probable budget.
- We explore what tasks or scope of work the owner will do, if any. This may include site prep work, dirt fill, electrical and lighting done by local contractors, landscaping, irrigation and point-of-sale (POS) kiosk.
- A conference call can be done in less than one day, however the owner will have to produce more site information, such as a site survey CAD plan with topography, city / county setbacks, environmental issues (if any), etc. all of which can take additional time.
- AGS Concept and Positioning Plan – This is the first design to allow for space allocation of all elements in the plan including golf holes, walkways, water features, theming and anything else. This process can take 7 to 14 business days after it is scheduled.
- Design Conference with owner to discuss and make changes to the Concept and Positioning plan and discuss probable budget range. 1 – 3 business days.
Final design of miniature golf course and final budget. 7 – 14 business days.